HMMC resumes production in Nošovice

Published: 20.05.2020 Related countries:  Czech Republic Czech Republic

Hyundai Motor Manufacturing Czech (HMMC) resumed production in its Nošovice plant on April 14.

Hyundai Motor Manufacturing Czech (HMMC) resumed production in its Nošovice plant on April 14, 2020, following a shutdown due to the COVID-19 pandemic. To ensure a smooth start, the carmaker starts with two-shift operation with alternating morning and afternoon shifts. Employees who are allocated a night shift in each given week receive 70% of their average earnings compensation. The plant is extraordinarily partially pre-stocked with parts, which normally is not done in the just in time system. The facility is disinfected several times a day. Employee meetings are also limited.